Sylvan Circle & E. Porter Avenue Watermain and Roadway Improvement Project

September 6 Update

All new sanitary sewer and water main utilities are complete. The utility contractor plans to finish all storm sewer installations next week, weather permitting. The roadway contractor has completed pavement excavation and stone roadway base installation along Porter from Julian to Sylvan. The next step for this section of roadway is to install the concrete curb, which will begin on Monday, 9/9. Once the curb is poured for this section of roadway, the contractor will continue the pavement excavation and stone roadway base installation for the remainder of Porter and Sylvan. We are currently on schedule for pavement installation in October, barring any unforeseen circumstances. Please continue to use caution while traveling in the area and follow all signage, flaggers, and posted detours. Please have patience with our contractors as you attempt to enter and leave the neighborhood, as they are doing everything in their power to work quickly, efficiently and safely.

The City Department of Water/Wastewater has identified the need to upgrade the existing watermain along Sylvan Circle and E. Porter Avenue and, as a partner on this project, the Transportation, Engineering, and Development Department has identified the need to improve Sylvan Circle and E. Porter Avenue Roadways. The goal of this project is to upgrade and loop the watermain providing better water flow, pressure, and circulation while also creating a better driving experience for motorists by addressing certain aspects of the substandard roadways. 

The project includes replacing approximately 3000-feet of watermain and providing a looped connection which currently does not exist. The potential roadway improvement options are widening and re-aligning the roadway; installing new pavement, curbs and gutters, storm sewer system; and installing a new street lighting system. Additionally, an option of installing sidewalk will be reviewed with public input taken into consideration.

Construction Layout Beginning

Beginning in late April, residents will begin seeing wooden stakes that will assist the contractor.  Please do not remove wooden stakes or flags that are being placed. The stakes were set specifically outside of the construction limits so they would not be disturbed and do not represent how far into yards construction will go. The surveyors will stake points for construction fencing later next week. When the fencing is up, it will provide boundaries for the contractor to work within.

Tree Removal

Tree removal is scheduled to begin in late April, weather-dependent.  Two different colored dots have been placed on trees in or near the construction work zone. Pink colored dots have been placed on trees that are to be removed. Green colored dots have been placed on trees requiring limb pruning in order to provide adequate work space for the contractor. As stated during public meetings, a certified arborist will be on site for all tree removal/pruning.